Pagabo 2026 results · Time sensitive

Pagabo standstill period: what to do with your assessment summary before it ends

By Jean-Pascal Olivier, Co-Founder and Director, Glaxtons Consulting. Published 9 October 2026.

For the Pagabo Developer-Led framework the standstill period ends at 23:59 on 15 October 2026. Assessment summaries went out on 5 October, the award notice was published on 6 October, signature is scheduled for 16 October and the framework starts on 19 October. If you were not appointed you have days, not weeks, to decide whether to challenge and what to do next.

The dates, from the notice

These are read from award notice 094430-2026. Major Works and Civils bidders should use the date in their own assessment summary, which may differ.

6 days left on the Developer-Led standstill period.

  1. 5 October 2026Assessment summaries sent to bidders
  2. 6 October 2026Contract award notice published on Find a Tender
  3. 15 October 2026Standstill period ends at 23:59
  4. 16 October 2026Framework agreement scheduled for signature
  5. 19 October 2026Framework term starts, running to 19 October 2030

Source: Find a Tender contract award notice 094430-2026 , published 6 October 2026, read on 2026-10-09 with scripts/pagabo_results.py. Bids are the lot bids recorded in the notice. Only counts are shown; unsuccessful bidders are not named.

A plan for the days that are left

  • Day one: read the assessment summary line by line. List every criterion where you scored below the maximum, and note any score that looks wrong or inconsistent with your own submission.
  • Day two: compare each low score with what your submission actually said. Mark whether the evaluator missed something that was there, or whether it was never there.
  • Day three: take the findings to a procurement solicitor if there is any prospect of a challenge. They will tell you whether the facts support a claim and what the standstill date means for timing.
  • Day four onward: put the challenge question aside and plan the route. Appointed firms are about to start call-offs and will be hiring capacity.

What a challenge needs

A challenge needs evidence that the process was applied wrongly, not that you disagree with the score. The strongest grounds are factual errors, an evaluator applying criteria not in the published documents, or inconsistent treatment between bidders. A lower score than you hoped is not, on its own, a ground.

We are not a law firm and we do not give legal advice. We prepare the scoring analysis and a side-by-side of your submission against the criteria in 24 to 48 hours, which is what a solicitor needs to give you a view quickly.

What most suppliers do instead

Most unsuccessful bidders do not challenge. They use the assessment summary to find where they lost marks and aim at the next opportunity. That is a sound decision, as long as the next opportunity has a date. The live frameworks and the supply chain route are set out in the three routes back in.

Questions suppliers ask

When does the Pagabo Developer-Led standstill end?

At 23:59 on 15 October 2026, per Find a Tender award notice 094430-2026. The framework agreement is scheduled for signature on 16 October and the term starts on 19 October 2026.

How long is a standstill period under the Procurement Act 2023?

At least eight working days from the date assessment summaries are sent. For the Developer-Led framework, summaries went out on 5 October and the standstill ends on 15 October, which is eight working days.

Can Glaxtons challenge a Pagabo result for me?

No. We are not a law firm. We review your assessment summary and submission and produce the scoring analysis a procurement solicitor needs, usually in 24 to 48 hours.

Missed a Pagabo place, or have a deadline inside two weeks?

Send us your availability for a Microsoft Teams call. Bring your assessment summary or your tender pack and we will tell you, in that first conversation, what the data says about your position and which route is worth your time. If a deadline cannot be met we will say so before any fee is agreed.

Our record: a 93 per cent success rate across 500 plus submissions, 2022 to 2025, against an industry average of 60 to 75 per cent (APMP and Bid Solutions).

Send us your assessment summary or your deadline

Tell us which framework or tender, the date that matters and what you have. A director replies the same working day with a straight view.

Or call us directly: 020 3668 5488

Keep reading

Sources

Professional Bid Writing Services UK. 93% Success Rate.

Expert bid consultancy and tender writing for government, NHS and CCS frameworks. £500M+ contracts won. Same-day response. 24/7 urgent support.

Get a Free Quote. Same Day Response. ☎ 020 3668 5488
✓ 93% Success Rate ✓ £500M+ Won ✓ 500+ Tenders ✓ 2-Hour Response

Recent Wins

✓ Won £45M NHS FM contract for healthcare provider

✓ Secured £12M MoD framework for defence SME

✓ Won £8M G-Cloud lot for SaaS company